The latest A6MARR scheme road markings and landscaping drawings can be found below.

The A6MARR’s package of Complementary and Mitigation measures to address changes to traffic flows in the local area as a result of the scheme and enhance the wider walking and cycling network is being developed by the three local authorities. Further information can be found on the Complementary and Mitigation Measures page.

Public Consultation on Proposed Extension to Earthworks Mounds 11th November to 2nd December

During the construction of the A6 to Manchester Airport Relief Road (A6MARR), the contractor, Carillion Morgan Sindall, has identified an opportunity to provide additional screening of the new road by new or extended earthwork mounds (also known as bunds) in locations across the scheme.  The A6MARR Project Team would like to seek the views of residents of adjacent properties to these proposed extended and new bunds prior to the submission of planning applications to the Local Planning Authorities, Cheshire East, Stockport and Manchester City councils.

You may be aware that in the A6MARR planning application it stated that the scheme design achieved an earthworks balance i.e. any earth that needed to be dug out during construction could be placed elsewhere on the scheme in the form of earthwork bunds. However, following further assessment of the ground conditions subsequent to the planning application being approved, a change in the construction methodology has been required, meaning that more earth has become available to provide additional screening to adjacent properties.

In addition to providing additional screening, the extension of the bunds allows more material can be retained on site, thereby mitigating the traffic and environmental impacts of transporting the large volumes of material off site by the local road network.

The bunds will be grassed over and landscaped to provide appropriate visual mitigation. Where possible, the planting on the extended bunds will be as per the landscaping proposals submitted as part of the original planning application for the A6MARR (see A6MARR.stockport.gov.uk).  Landscaping proposals for the new bunds are currently being developed and will be informed by the feedback received as part of this consultation.

Drainage provision will be reviewed and appropriate drainage designed and constructed.

Have your say

We are holding a series of exhibitions to provide an opportunity for you to speak to members of the A6MARR Project Team and view plans showing the proposed changes to the bunds.  Details of the exhibitions are as follows:

Date Venue Address Time booked
Tuesday 15th November Queensgate Primary School Albany Road, Off Meadway,
Bramhall,
Stockport,
SK7 1NE
Exhibition 3 pm until 7 pm)
Wednesday 16th November Heald Green Village Hall Outwood Road
Heald Green
Cheadle
SK8 3JL
Exhibition 3 pm until 7 pm
Monday 21st November Chester Road Compound Site Office
Chester Road
Poynton
SK12 1DS
Exhibition 5 pm until 7 pm
Monday 28th November Hazel Grove Civic Hall London Road
Hazel Grove
SK7 4DF
3 pm until 7pm
Bund Descriptions and Drawings – Styal Road to Wilmslow Road

The location of the bunds is shown in the location plan. With reference to the plan, a description on the bunds is provided in the table below.

Site Description
1 Site located north-east of proposed A6MARR-Styal Road junction.

Proposed new earth mounding (bund) designed to avoid new drainage attenuation tank and existing trees and vegetation.  Proposed earthwork mound up to 4.0m in height over the existing ground level.

15 Site located to the east of A6MARR-Styal Road junction, adjacent to the electricity substation.

Proposed new earthwork mound to extend the A6MARR embankment to fill area of land adjacent to the A6MARR carriageway.  Mound height up to approximately 5.6m above existing ground level.

20 Site located to the south-east of Styal line Railway Bridge, adjacent the south side of the A6MARR carriageway.

Proposed to re-profile and increase the height of the approved earthwork mound that is located here to screen views of the scheme.  Proposed height increase to the approved mound of approximately 1.4m.

18 Site located north-east of Styal golf Course, south of the A6MARR, and immediately east of Yew Tree footbridge.

Proposed mound comprises an extension to the already approved earthwork which forms the approach to the footbridge extension and provides screening of the scheme.  The mound would be increased in height by up to about 3.4m over that currently approved and would be re-profiled to make it more natural in form.

19 Site located north-east of Styal golf Course, north of the A6MARR, and immediately east of Yew Tree footbridge.

Proposed mound comprises an extension to the already approved earthwork which provides screening of the scheme.  The mound would be increased in height by up to about 1.5m (at the eastern end) over that currently approved and would be re-profiled to make it more natural in form.

 Drawings showings the landscaping of the bunds are provided below.

Drawing Reference Title
A6MARR-1-W-100-SK-914-A Additional And/Or Extended Earthworks Bund Site 1 Landscape Design
A6MARR-1-W-100-SK-913-A0 Additional And/Or Extended Earthworks Bund Site 15  Landscape Design
A6MARR-1-W-100-SK-918-A0 Additional And/Or Extended Earthworks Bund Site 20 Landscape Design
A6MARR-1-W-100-SK-917-A1 Additional And/Or Extended Earthworks Bund Sites 18 & 19 Landscape Design

Drawings showing the location and cross sections of the bunds are provided below

Drawing Reference Title
A6MARR-1-W-100-SK-114-A1 Bund Site 1 Additional and/or Extended Earthworks Bunds Plan and Cross Sections
A6MARR-1-W-100-SK-113-A1 Bund Site 15 Additional and/or Extended Earthworks Bunds Plan and Cross Sections
A6MARR-1-W-100-SK-118-A1 Bund Site 20 Additional and/or Extended Earthworks Bunds Plan and Cross Sections
A6MARR-1-W-100-SK-117-A1 Bund Site 18 & 19 Additional and/or Extended Earthworks Bunds Plan and Cross Sections

Bunds Locations – Woodford Road, Bramhall to A6, Hazel Grove

The location of the bunds is shown in the location plan. With reference to the plan, a description on the bunds is provided in the table below.

Drawings showings the landscaping of the bunds are provided below.

Drawing Reference Title
A6MARR-1-W-100-SK-910-A Additional And/Or Extended Earthworks Bund Site 5 Landscape Design
A6MARR-1-W-100-SK-907-A0 Additional And/Or Extended Earthworks Bund Site 12 Landscape Design
A6MARR-1-W-100-SK-909A-A2 Additional And/Or Extended Earthworks Bund Site 25 & 26 Landscape Design
A6MARR-1-W-100-SK-908A-A1 Additional And/Or Extended Earthworks Bund Site 16 Landscape Design
A6MARR-1-W-100-SK-908-A1 Additional And/Or Extended Earthworks Bund Site 5A Landscape Design
A6MARR-1-W-100-SK-911-A1 Additional And/Or Extended Earthworks Bund Site 13 Landscape Design
A6MARR-1-W-100-SK-919-A1 Additional And/Or Extended Earthworks Bund Site 13A Landscape Design
A6MARR-1-W-100-SK-927-A0 Additional And/Or Extended Earthworks Bund Site 21 Landscape Design
A6MARR-1-W-100-SK-905-A0 Additional And/Or Extended Earthworks Bund Site 8 Landscape Design
A6MARR-1-W-100-SK-906-A0 Additional And/Or Extended Earthworks Bund Site 9/9A Landscape Design
A6MARR-1-W-100-SK-928-A0 Additional And/Or Extended Earthworks Bund Sites 22, 23, 24 Landscape Design
A6MARR-1-W-100-SK-903-A0 Additional And/Or Extended Earthworks Bund Site 11 Landscape Design
A6MARR-1-W-100-SK-908B-A1 Additional And/Or Extended Earthworks Bund Site 17 Landscape Design

Drawings showing the location and cross sections of the bunds are provided below.

Drawing Reference Title
A6MARR-1-W-100-SK-110-A1 Bund Site 5 Additional and/or Extended Earthworks Bunds Plan and Cross Sections
A6MARR-1-W-100-SK-107-A0 Bund Site 12 Additional and/or Extended Earthworks Bunds Plan and Cross Sections
A6MARR-1-W-100-SK-109A-A3 Bund Site 25 and 26 Additional and/or Extended Earthworks Bunds Plan and Cross Sections
A6MARR-1-W-100-SK-108A-A3 Bund Site 16 Additional and/or Extended Earthworks Bunds Plan and Cross Sections
A6MARR-1-W-100-SK-108-A3 Bund Site 5A Additional and/or Extended Earthworks Bunds Plan and Cross Sections
A6MARR-1-W-100-SK-111-A0 Bund Site 13 Additional and/or Extended Earthworks Bunds Plan and Cross Sections
A6MARR-1-W-100-SK-119-A1 Bund Site 13a Additional and/or Extended Earthworks Bunds Plan and Cross Sections
A6MARR-1-W-100-SK-127-A0 Bund Site 21 Additional and/or Extended Earthworks Bunds Plan and Cross Sections
A6MARR-1-W-100-SK-105-A1 Bund Site 8 Additional and/or Extended Earthworks Bunds Plan and Cross Sections
A6MARR-1-W-100-SK-106-A1 Bund Site 9-9A Additional and/or Extended Earthworks Bunds Plan and Cross Sections
A6MARR-1-W-100-SK-128-A0 Bund Sites 22, 23, 24 Additional and/or Extended Earthworks Bunds Plan and Cross Sections
A6MARR-1-W-100-SK-103-A0 Bund Site 11 Additional and/or Extended Earthworks Bunds Plan and Cross Sections
A6MARR-1-W-100-SK-108B-A1 Bund Site 17 Additional and/or Extended Earthworks Bunds Plan and Cross Sections
Bund Descriptions and Drawings – Woodford Road, Bramhall to A6, Hazel Grove

The location of the bunds is shown in the location plan. With reference to the plan, a description on the bunds is provided in the table below.

Drawings showings the landscaping of the bunds are provided below.

Drawing Reference Title
A6MARR-1-W-100-SK-910-A Additional And/Or Extended Earthworks Bund Site 5 Landscape Design
A6MARR-1-W-100-SK-907-A0 Additional And/Or Extended Earthworks Bund Site 12 Landscape Design
A6MARR-1-W-100-SK-909A-A2 Additional And/Or Extended Earthworks Bund Site 25 & 26 Landscape Design
A6MARR-1-W-100-SK-908A-A1 Additional And/Or Extended Earthworks Bund Site 16 Landscape Design
A6MARR-1-W-100-SK-908-A1 Additional And/Or Extended Earthworks Bund Site 5A Landscape Design
A6MARR-1-W-100-SK-911-A1 Additional And/Or Extended Earthworks Bund Site 13 Landscape Design
A6MARR-1-W-100-SK-919-A1 Additional And/Or Extended Earthworks Bund Site 13A Landscape Design
A6MARR-1-W-100-SK-927-A0 Additional And/Or Extended Earthworks Bund Site 21 Landscape Design
A6MARR-1-W-100-SK-905-A0 Additional And/Or Extended Earthworks Bund Site 8 Landscape Design
A6MARR-1-W-100-SK-906-A0 Additional And/Or Extended Earthworks Bund Site 9/9A Landscape Design
A6MARR-1-W-100-SK-928-A0 Additional And/Or Extended Earthworks Bund Sites 22, 23, 24 Landscape Design
A6MARR-1-W-100-SK-903-A0 Additional And/Or Extended Earthworks Bund Site 11 Landscape Design
A6MARR-1-W-100-SK-908B-A1 Additional And/Or Extended Earthworks Bund Site 17 Landscape Design

Drawings showing the location and cross sections of the bunds are provided below.

Drawing Reference Title
A6MARR-1-W-100-SK-110-A1 Bund Site 5 Additional and/or Extended Earthworks Bunds Plan and Cross Sections
A6MARR-1-W-100-SK-107-A0 Bund Site 12 Additional and/or Extended Earthworks Bunds Plan and Cross Sections
A6MARR-1-W-100-SK-109A-A3 Bund Site 25 and 26 Additional and/or Extended Earthworks Bunds Plan and Cross Sections
A6MARR-1-W-100-SK-108A-A3 Bund Site 16 Additional and/or Extended Earthworks Bunds Plan and Cross Sections
A6MARR-1-W-100-SK-108-A3 Bund Site 5A Additional and/or Extended Earthworks Bunds Plan and Cross Sections
A6MARR-1-W-100-SK-111-A0 Bund Site 13 Additional and/or Extended Earthworks Bunds Plan and Cross Sections
A6MARR-1-W-100-SK-119-A1 Bund Site 13a Additional and/or Extended Earthworks Bunds Plan and Cross Sections
A6MARR-1-W-100-SK-127-A0 Bund Site 21 Additional and/or Extended Earthworks Bunds Plan and Cross Sections
A6MARR-1-W-100-SK-105-A1 Bund Site 8 Additional and/or Extended Earthworks Bunds Plan and Cross Sections
A6MARR-1-W-100-SK-106-A1 Bund Site 9-9A Additional and/or Extended Earthworks Bunds Plan and Cross Sections
A6MARR-1-W-100-SK-128-A0 Bund Sites 22, 23, 24 Additional and/or Extended Earthworks Bunds Plan and Cross Sections
A6MARR-1-W-100-SK-103-A0 Bund Site 11 Additional and/or Extended Earthworks Bunds Plan and Cross Sections
A6MARR-1-W-100-SK-108B-A1 Bund Site 17 Additional and/or Extended Earthworks Bunds Plan and Cross Sections
Responding to the consultation

Attend an exhibition (see details above)

Email: SEMMMS.Relief.Road@stockport.gov.uk

Telephone: 0161 474 2055 (24hr, 7 days a week)

Post: SEMMMS Project Team, Stockport Council, Stopford House (Fred Perry), Stockport SK1 3YQ.

If you have any questions about the proposed changes to the bunds, please do not hesitate to contact us by any of the above methods.

Please provide your feedback by 2nd December 2016.

The comments received as part of this consultation will be considered in the development of the proposals prior to the planning applications being submitted to the Local Planning Authorities.

A6MARR Construction Supply Chain

The Carillion Morgan Sindall joint venture (CMS) has been appointed by Stockport Council to undertake the detailed design and construction of the A6 to Manchester Airport Relief Road (A6MARR). Carillion and Morgan Sindall are national contractors, which are based in Trafford Park and Salford respectively, undertaking major construction and infrastructure projects.
 
A joint venture between consultants Aecom and Grontmij is subcontracted to CMS and is responsible for design development and detailed design of the scheme.
 
The supply chain for the construction of the A6MARR is also made up of a number of other subcontractors and suppliers, as listed below.